Final design of a wind power plant located in the municipality of Casalduni (BN), for a nominal power of 1 MW. Completion of 1 MW plant Location: Casalduni (BN) “San Fortunato” 1 (1 MW) Wind power generator | Installed Capacity: 1 MW Year built: 2014
Campolattaro (BN) – Zingara Morta
Final design of a wind power plant located in the municipality of Campolattaro (BN), for a nominal power of 1 MW. Completion of 1 (1 MW) plant Location: Campolattaro (BN) “Zingara Morta” 1 (1 MW) Wind Power Generator | Installed Capacity: 1 MW Year built: 2014
Pontelandolfo (BN) – Malepara
Final design of a wind power plant located in the municipality of Pontelandolfo (BN), for a nominal power of 1 MW. Completion of 1 (1 MW) plant Location: Pontelandolfo (BN) “Malepara” 1 (1 MW ) Wind Power Generator | Installed Capacity: 1 MW Year built: 2014
Campolattaro (BN) – Colle Serra
Riassunto di Campolattaro
Pescina (AQ)
Wind Farm site in Collarmele. In the Velino-Sirente Regional Park, with a revamping of the wind farm in the Collarmele-Cerchio district, the largest wind farm in Abruzzo was installed. The old single blade wind turbines were replaced with 2 MW machines to reach 12 MW of power. 6 farms were installed. Cerchio (AQ) 6 (2 MW) Wind
Cerchio (AQ)
Wind Farm site in Collarmele. In the Velino-Sirente Regional Park, with a revamping of the wind farm in the Collarmele-Cerchio district, the largest wind farm in Abruzzo was installed. The old single blade wind turbines were replaced with 2 MW machines to reach 12 MW of power. 6 farms were installed. Location: Cerchio (AQ) 6 (2 MW)
Collarmele (AQ) – II
Wind Farm site in Collarmele. In the Velino-Sirente Regional Park, with a revamping of the wind farm in the Collarmele-Cerchio district, the largest wind farm in Abruzzo was installed. The old single blade wind turbines were replaced with 2 MW machines to reach 12 MW of power. 6 farms were installed. Location: Collarmele (AQ) – II “Monte Coppetella”
Collarmele (AQ) – I
Wind Farm site in Collarmele. In the Velino-Sirente Regional Park, with a revamping of the wind farm in the Collarmele-Cerchio district, the largest wind farm in Abruzzo was installed. The old single blade wind turbines were replaced with 2 MW machines to reach 12 MW of power. 6 farms were installed. Collarmele (AQ) – I “Costa Miucci” 6 (2MW)